Skip to main content Skip to search Skip to main navigation
Menu

Initial Setup

Step-by-step instructions and video tutorials for a perfect start.

22 Inch System Guide

5 Inch System Guide

1

Unpacking

Unpack carefully. Roof sections might be delivered separately.

2

Inspection

Check for transport damage immediately and report if necessary.

3

Safety Locks

Carefully remove zip ties from the product trays.

4

Power

Connect directly to a 230V outlet (no power strips).

5

Opening

Use the key in the coin slot. Check the main switch at the bottom.

6

Startup

Wait for system processes to complete.

7

Password

Change the default admin password in Sys-Settings immediately.

9

Coin Changer

Fill with change and calibrate the unit.

10

Reboot

Turn off for 60s, then switch back on.

11

Filling

Pull out product trays and fill compartments.

13

Stock

Enter current stock & capacity for each slot.

14

Testing

Test dispensing and payment modules several times.

15

Nayax Setup

Set up Nayax Core Portal and sync inventory.

Still have questions?